Following the award of an $8.15 million infrastructure grant from the Michigan Department of Education, Engadine Consolidated Schools is moving into the planning and design phase for critical improvements to its K–12 building.

The grant will support repairs and upgrades informed by professional facility assessments and identified by the Michigan Department of Education (MDE), including roofing, HVAC systems, electrical systems, accessibility, safety and security, plumbing, and site improvements. MDE determined the funding assigned to each project category as part of the grant award.

The design process began in October 2026 with a design team kickoff and project planning. Early work included reviewing the approved project scopes, selecting the design team, establishing the project schedule, and coordinating building scanning.

Current planning and design schedule includes:
-October 2026: Design team kickoff and project planning
-October 2026 through December 2027: Schematic design, building scanning, development of design options, and programming
-January through March 2027: Design development and finalization of project scopes
-April through June 2027: Preparation of construction documents and construction planning
-August 2027: Public bidding
-Summer 2028: Anticipated construction season

The schedule may change as the design process moves forward. Construction work is expected to be completed before the grant expenditure deadline of September 30, 2028.

“This is an important next step in putting this grant to work for our students, staff, and community,” said Superintendent Heather Luoto.

“The planning and design process will help us carefully develop the projects supported by the grant and prepare for construction. We are grateful for this opportunity to improve the safety, comfort, efficiency, and long-term use of our school building.”

The district also plans to create a Facility Improvements + Planning webpage in the future. The webpage will provide families, staff, and community members with information about the project, planning updates, the design schedule, and construction progress.

—Heather Luoto, Superintendent